8Way TP&N Power & Lighting Distribution Board
8Way TP&N Power & Lighting Distribution Board
Neatly installed distribution board feeding office power & lighting.
See progress below.




A Simple 3 phase distribution board installed to trunking, circuits wired in twin & earth for ease of wiring.
Circuits stripped/sleeved & marked and neatly connected into the correct terminals with care.
Switch Room Installation
Switch Room Installation
24 way MCCB Panel with check meters.
See progress below.





Surge protection supply being connected to busbar.
Picture 1
Swa cables being stripped and terminated into breakers.
Pictures 2,3&4
Dead Testing
Dead Testing
Fault: Short circuit on cleaners sockets between Neutral and Earth


Testing With Pin Point Accuracy
Testing With Pin Point Accuracy
Exposing potential damaging screw.
Removing First Layer of Board
Removing First Layer of Board
Removal of first sheet of plaster board, revealing partition line


Finding The Fault With Minimum Damage
Finding The Fault With Minimum Damage
Cables had been pulled in front of partition and damaged by screw when dry liners installed plasterboard.